Dallas Road Closures Postponed until 14 August

Author: 
Chris Satori

Dallas Road roadworks have been posponed.  Minor works are to commence early next week but the road closure will not start until Monday 14 August whilst planing and resurfacing work are carried out.

The works were supposed to commence last week but due to the heavy rainfall and flooding in places the work was suspended. 

Lancashire County Council has allocated £106,000 from efficiency savings for resurfacing the full length of Dallas Road. The work has been scheduled to take place in the school summer holiday period while traffic levels are lower to minimise disruption.

Closures could go on for 5 weeks. Dallas Road will re-open at the earliest opportunity. The work is scheduled to finish in early September and is expected to be completed on time.

A signed diversion will be in place via Meeting House Lane, King Street and Carr House Lane.

 

 

: